| Milestones
& Activities |
Start |
Finish |
| 1. Project Initiation & Work Plan |
May 1 |
June 29 |
| 2. Hire Planning Team & Establish Community Advisory Group |
June 11 |
July 6 |
2a. Community Advisory Group Meetings
Approx. once/month mid-June to mid November 2007 |
June 12 |
Dec 15 |
| 3. Land Tenure Research & Background Information Compilation |
May 28 |
Aug 30 |
| 4. Survey & Base Map Development |
June 28 |
July 20 |
5. Individual Stakeholder Meetings
- Carcross RCMP
- Yukon Government – Highways & Public Works, EMR- Lands, Land Claims Implementation Secretariat, Community Services (Protective Services & Community Development), Tourism & Culture: Heritage, VIC & Tourism Development, Environment
- Parks Canada
- CTFN
- White Pass
- SKLAC
- Chamber of Commerce & members
- Tourism Industry Association Yukon (TIA)
- Destination Carcross
- Others??
|
July 3 |
Aug 15 |
| 7. On-site Observation – Pedestrian & Vehicular Patterns/Movement + Vehicle Count |
Jul 9 |
Sep 15 |
8. Public Input
Public Meeting #1 (Meet & Greet + Project Overview)
Public Input Sessions (#2): “Display” with facilitator set up in 2-3 locations in Carcross – public can write, draw and provide input into plan
Public Meeting #3 (present 2 to 3 plan options) |
July 12
July 12
Sep 15
Wk Oct 29 |
Nov |
| 9. Final Plan |
Oct 29 |
End Nov |